LITICE SMALL HYDRO POWER PLANT COMMISSIONED

In December 2015 tests on site, commissioning and training of electro-mechanical equipment on LITICE Power Plant on Labe river in the Czech Republic (1 x vertical Kaplan turbine, 1,280 kW, incl. LV and MV electrical equipment, and civil works) was performed successfully under the attendance of representatives of Povodí Labe s.p. Official signature of the Taking Over Certificate is expected within upcoming days.